CHUFFINGHAM under CONSTRUCTION

July 2024, the start above

Current project to the right

.

.

2026 JANUARY 21st

2026 JANUARY 10th

2026 JANUARY 1st.

2025 SEPTEMBER 13/14

2025 SEPTEMBER 10th.

2025 AUGUST 15/16th.

2025 AUGUST 8th.

2025 APRIL 4/5

2025 MARCH 22/23rd.

The wiring all works

The station buildings will fit nicely here

Our motley test crew minus the photographer!

Can we run 4 4-car multiple units at once?

2025 MID FEBRUARY

The access lift-bridge getting built and track added.

The access lift-bridge in place, track down, tested

2025 MID FEBRUARY

A block diagram of how the switch controls work.

2025 JANUARY 30th.

Wiring up the Shift Register boards.

2025 JANUARY 25th.

The power bus (snake) for the scenic boards

Working on the ‘snake’ is getting messy.

Wiring the ‘snake’ into the Power Distribution Box

Splicing leads in the ‘snake’ for a board plug

The Power Distribution box is getting messy.

Plug installed

2025 JANUARY 7th

PCA9685 and ESP32 ‘node’ installed

Under the board, track power wiring, servos and their leads, and the ‘node’ all installed in the Canal sections.

2024 DECEMBER

Hard at work installing the servos for changing points( British for turnout or switches)

2024 DECEMBER

The ‘Canal’ boards finally connected for track and wiring testing.

2024 DECEMBER

Trial track spacing for fiddleyard

Trail spacing for track and cassettes on the fiddleyard.

2024 NOVEMBER

Getting the track down on the ‘Canal’ scenic section, and wiring track power ‘droppers;

2024 OCTOBER

Getting track down on the first boards in the ‘Canal’ section of the layout.

Using foam sections to start the incline of the main lines to have raised tracks on the front boards

2024 SEPTEMBER 6TH.

Track laying on SCARM track plans at Heritage Park’s “”Railway Days”

2024 SEPTEMBER 1st.

2024 JULY 31st

2024 JULY

2024 WINTER, SPRING

2023 NOVEMBER

2023 SEPTEMBER

Scroll to Top